Housing Pieces Delayed
The Wall Street Journal
By Eliot Brown
The promise of more than 4,000 units of low- and middle-income housing was a significant selling point for two of the city's largest new developments, Atlantic Yards in Brooklyn and Willets Point in Queens.
Today, they are moving forward, but the housing pieces have been pushed back for years behind other portions of the multibillion-dollar projects, as the boom-era visions are proving to be difficult to see through in a slowly recovering economy.
...
At Atlantic Yards, the project's centerpiece basketball arena is nearing completion. But developer Forest City Ratner Cos. has yet to begin any of the 6,400 units of housing it once anticipated being built by 2016—2,250 of which would be for low- and middle-income families. Forest City has cited higher than expected costs and an inclement market, although it plans to break ground this year on its first building with 175 below-market rate units.
The delays have frustrated officials and given fuel to critics of the project, which went through a contested public approval process before the recession.
"They should do the affordable housing up front, now," said Assemblyman James Brennan of Brooklyn, who said the low- and middle-income housing aspects should be accelerated. "The only legitimate selling point for the entire project was the affordable housing."