« A day after losing out on Anthony, Nets get superstar point guard Williams; he's got a contract extension to sign, but for now, it's seen as a big win | Main | Flashback, 2006, Gargano interview: "This site is dormant. It's on a railyard" and "the improvements... will benefit all the people from that area" »

February 24, 2011

Reopening of Carlton Avenue Bridge, closed since January 2008 (supposedly for two years), nudged from April 2012 to "summer 2012"; will it go longer?

Atlantic Yards Report

It was inevitable, wasn't it? We knew that the Carlton Avenue Bridge, closed since January 2008, had to reopen before the Atlantic Yards arena reopens.

And now that "substantial completion" of the arena is August 12, 2012, so too has the city Department of Transportation nudged back the reopening of the bridge from the most recent deadline, April 2012, to "summer 2012."

That's not the first revision of the plan, not by a long shot.

And I'd say there's a good chance that the bridge reopening could be nudged further back to "fall 2012," if the arena opens in the fall.

Closure for four-and-a-half years?

All this means that bridge would be closed for at least four-and-a-half years, more than twice as long as originally promised in the Atlantic Yards environmental review, approved in 2006.