Scrambling to get the Barclays Center in operating shape--if not final shape--in time for the grand opening on September 28, Forest City Ratner officials today acknowledged that they were behind in what was already a tight schedule.

The "substantial completion date," when the arena would get a temporary certificate of occupancy (TCO) from the city Department of Buildings has been nudged back several times, in April 2011 from Aug. 12 to Aug. 27, and in February 2012 to Sept. 5, yesterday.

And even though the construction monitor for arena bondholders, Merritt & Harris, has dutifully reported that Sept. 5 date, most lately in a report dated 8/7/12, now the goal is sometime next week.

“The schedule for turnover by Hunt [Construction] to Forest City is today," Forest City executive Jane Marshall said this morning at a meeting of the Atlantic Yards District Service Cabinet, a bi-monthly meeting of involved agencies. "There is--that's not a deadline for them, they don’t get penalized... they earn something if they do it by certain dates... We think, in general, the arena is on track for getting a TCO probably next week. And at that point it will be turned over to arena operations. And I’m not sure when the permanent C of O would be--it doesn't need to be [there] for opening.”