Latest consultant's report: arena on schedule for "substantial completion" September 5; no mention of challenge in preparing for operations

Atlantic Yards Report

The Barclays Center arena is still on track for substantial completion on September 5, with a temporary certificate of occupancy, based on the latest report from Merritt & Harris, the construction monitor for the arena bond trustee. Several components of the arena are targeted to be completed by August 29.

There was no mention of any challenge in preparing the arena for operation; Forest City Ratner Executive VP MaryAnne Gilmartin once said in an affidavit that "it takes at least three to four months to commission an arena like Barclays Center--i.e., to test and refine the various buildings systems and the various operations (such as security and food services) that must be performing properly and efficiently." That meant the arena had to be completed by early July 2012--a date already in the past.

The Merritt & Harris report dated 8/7/12 and made available yesterday, is based on a 6/26/12 visit and documents made available on 7/20/12. (There's a bit of a time lag. Future site observations were scheduled for July 26, August 23, and September 27--the latter a day before arena opening.)