From the latest Construction Alert: progress on multiple fronts, but also the need for late-night and weekend work

Atlantic Yards Report

There's not much dramatic in the latest two-week Atlantic Yards Construction Alert, dated 7/16/12 (and embedded below) and released yesterday by Empire State Development after preparation by Forest City Ratner.

According to the document, there's progress on numerous fronts, including testing of an escalator in the new subway entrance, erection of steel for the Carlton Avenue Bridge, and access to the Flatbush Avenue sidewalk.

Then again, as stated in recent documents, "overall schedule maintenance" (aka finishing the arena in September for a Sept. 28 opening, and getting the Carlton Avenue Bridge done by then) requires two and even three shifts, and weekend work, such as for pile drilling at the site for the first tower.

Note that "trenches for the power and broadcast cable are being installed [at the broadcast lot at dean street and Sixth Avenue] and will be encased in concrete," though Department of Transportation approval has not yet been granted and a Forest City executive last week said they'd stopped work pending approval.

Also, several passages that indicate work being completed or about to be completed are repeated verbatim from the previous alert, which indicates delays, bad editing, or both.