July 18, 2012
Consultant's monthly report: arena "slightly ahead of schedule" (not quite), Transit Connection behind (but not a problem); 550 workers (plus those at railyard)
Atlantic Yards Report
The latest Site Observation Report, issued yesterday by Merritt & Harris, the consultant that reports to the arena bond trustee, Empire State Development Corporation, and Forest City Ratner, declares "the Arena is slightly ahead of schedule, while the Transit Connection is currently 4 months behind its original schedule."
Of course, as the charts indicate, the arena is "slightly ahead of schedule" because they tweaked the schedule earlier this year.
The report, while issued yesterday is dated 7/9/12 and based on a 5/23/12 visit and documents dated 6/22/12.
Manpower
The report states, "According to the General Contractor and the Manpower Log, 550 persons have been on the job for the Arena and 48 persons for the Transit Connection this month." That's an increase from 490 and 48 in the previous report and is "attributed to the roofing, carpentry, and finish trades."
On 6/28/12, Patch quoted Forest City Ratner as having 1,079 employees on site, a number I couldn't get verified as full-time equivalent.
Even with a large crew at the railyard, which is not covered in the Merritt & Harris report (which examined documents dated less than a week before the Patch article), the total seems very doubtful.
Posted by eric at July 18, 2012 11:52 AM