« At clergy-led rally for arena justice, some new voices, some ironies, and a request for new oversight; "we're not just going to get caught up in the [Nets/Jay-Z] hype" | Main | Details from Barclays Center liquor license application: no info about after-hours service, but list of bars, entrances detailed, Jay-Z's role »

June 12, 2012

Report: schedule indicates Carlton Avenue Bridge delayed, but could meet arena opening date thanks to overtime; ESDC says "mitigation plan" reference incorrect; arena still on schedule for September 5; transit connection slips to mid-AugustThe report, dat

Atlantic Yards Report

The Carlton Avenue Bridge is still scheduled to be completed on 10/3/12, five days after the first event at the Barclays Center, but, according to a report from the construction monitor for the arena bond trustee, Forest City Ratner is paying overtime to meet the completion date, and also has asked the city Department of Transportation for the OK to open the bridge with temporary street lighting and railing.

The report, dated 6/4/12 and based on a site visit 4/26/12 and a later document review, was issued by Merritt & Harris, which reports to the bond trustee, developer Forest City Ratner, and the Empire State Development Corporation.

The report also states, "Nevertheless, the Empire State Development (ESD) has requested that FCRC propose a mitigation plan to control and alleviate the traffic flow congestion for the first event at the arena, scheduled for September 28, 2012."

Is that so? Arana Hankin, Director, Atlantic Yards Project, ESD, told me the report was wrong. Merritt & Harris, she suggested, might be referring to the Transportation Demand Management plan (TDM) developed by Forest City.

article

NoLandGrab: September 28th, October 3rd. Tomato, tomahto. Whatever the date, it's clear Forest City Ratner hasn't cared about "f**king the bridge."