Sleep tight: Railyard lights to be on all night to rush completion of delayed Carlton Avenue Bridge

Atlantic Yards Report

Ratner (and ESDC) to residents near Atlantic Yards site: "F**k you!"

Empire State Development, the state agency overseeing Atlantic Yards, today issued a Supplemental Report to its regular two-week Construction Updates.

The gist: floodlights at the Vanderbilt Yard that are supposed* to be off by 3 am may be on all night during the next two week period, in mid-June, and possibly through the end of June. That means residents nearby to ensure they have very thorough coverage blocking their windows.

Why'd I add the asterisk? Because residents have already reported, via Atlantic Yards Watch, that those operating the lights do not necessarily follow the stated plan.

The reason? Developer Forest City Ratner is rushing to achieve "timely completion" of the Carlton Avenue Bridge, indicated in the announcement by the rather cryptic initials CAB.

What's missing? That the current schedule for the bridge indicates completion in the week after the arena opens, though the reconstruction of the bridge is an "arena opening condition," and the state has asked Forest City Ratner to draw up mitigation plans in case the arena opens September 28 without having the bridge open. The bridge is a major artery between Prospect Heights and Fort Greene.