From the latest Construction Alert: a two-week (at least) closure of the Flatbush Avenue sidewalk west of Dean

Atlantic Yards Report

The latest two-week Atlantic Yards Construction Alert, dated 1/30/12, was distributed yesterday by Empire State Development (after preparation by developer Forest City Ratner).

There's not much dramatic in the alert, just indications of expected progress in various aspects of the project. Most notable to neighbors, perhaps, is this:

An 80’ section of the northern Flatbush Ave. sidewalk west of Dean St. will remain closed during this reporting period while façade installation is underway. This closure is due to agreement between NYCDOB [Department of Buildings] and Hunt [Construction].

Late-shift work

As in the previous alert, there will be double-shift and weekend work at the Long Island Rail Road/Vanderbilt Yard/ Carlton Avenue Bridge:

  • All weekdays all locations in the yard: 6:00AM to 11:00PM
  • Saturdays as required: 7:00 AM to 11:00 PM
  • Sundays and Holidays as required: 8:00AM to 11:00PM

And there may be late shift and overnight shift work at the arena site:

Subject to receipt of permits, a second shift shall be continued throughout this reporting period, from 3 – 11 PM, Monday-Friday only. Also subject to receipt of permits, a third shift may be instituted during this reporting period, from 11 PM – 7 AM, Monday–Friday only.