« First residential tower now delayed until spring or summer; Forest City admits "goal" of including more larger units won't be met; CM James says developer's not meeting commitment | Main | Transportation Demand Management plan for arena, originally due in December, then pushed to February, now expected in May; state official: "I think we're going to be OK" »

January 27, 2012

Forest City Ratner: Carlton Avenue Bridge "projected completion" early September; arena on schedule (no mention of report on delays); facade company catching up after temporary closure

Atlantic Yards Report

At yesterday's Atlantic Yards District Service Cabinet meeting, held at Borough Hall, Forest City Ratner officials gave several assurances about the timetable for ongoing work--but also left some questions lingering.

Carlton Avenue Bridge

Construction chief Bob Sanna provided an update on the Carlton Avenue Bridge, which is supposed to be reconstructed before the arena opens in September, thus reopening a long-closed connection between Prospect Heights and Fort Greene.

"The bulk excavation is 95% complete, there’s an extensive storm retention system that’s below the tracks. We have two of the three detention tanks now complete," he said. "The north abutment is about 60% complete, we started working on the south abutments."

"We expect to be able to cut over the yard, transfer trains into the newly laid track in February, and cover the trains over in May," he said, "which will allow us to complete the bridge in the early part of September. So the projected completion of the bridge... is the early part of September.”

That doesn't give them a lot of slack, given that the arena is supposed to open September 28, following several pre-opening events. I wrote earlier this month about the possibility of the schedule slipping, and the non-punitive penalties--a stall on starting a new tower--facing Forest City.

article

Posted by eric at January 27, 2012 11:22 AM