Barclays Center developer says show will go on

Despite the recent demise of the company fabricating the weathered-steel skin for the new home of Brooklyn Nets basketball team, the opening is still set for later this year.

Crain's NY Business
by Theresa Agovino

The developer of the Barclays Center arena in downtown Brooklyn says that the year-end demise of the company that is fabricating the weathered steel for the arena's distinctive façade will not result in any construction delays.
...

“We are concerned when any of our partners has problems, but we don't believe it will affect our construction schedule,” said MaryAnne Gilmartin, executive vice president of Forest City Ratner, referring to steel fabricator ASI Limited having gone out of business. “We can still continue with construction.”

In a statement, a spokesman for Forest City said the site's construction manager, Hunt, and the bonding company for ASI have developed an action plan. They have already started work on site and have developed several options for on-going fabrication. It didn't specify the options.

article

Related coverage...

Park Slope Patch, Barclays Center Will 'Open as Scheduled' Despite Steel Snafu: Ratner

According to Atlantic Yards Report, which first broke the story on Tuesday, ASI's apparent demise raised questions as to whether the remaining specialty steel would be delivered and how this might affect Barclays Center's tight construction timeline.

When contacted Thursday, Forest City Ratner spokesman Joe DePlasco dismissed those concerns, saying, "We do not think [ASI's closure] will aversely affect the timeline, and the arena is still planned to open as scheduled."

Curbed, It May Be Naked, But Barclays Will Take Stage

Not even the possibility of a calamitous costume snafu will prevent the new Barclays Center arena in Prospect Heights from making its scheduled debut at the start of the 2012-13 NBA season. Or so says Forest City Ratner, after subcontractor ASI Limited shut its doors and went out of businesses in late December.
...

Forest City Ratner says that it has developed several ongoing but unspecified alternatives for the fabrication of the necessary steel panels.

NoLandGrab: We've already suggested this alternative, but we'll repeat it in case MaryAnne Gilmartin missed it the first time around.

Posted by eric at January 6, 2012 11:58 AM