ATLANTIC YARDS RATNERVILLE CONSTRUCTION UPDATE
ATLANTIC YARDS CONSTRUCTION UPDATE
Weeks beginning November 17, 2008 and November 24, 2008In an effort to keep the Atlantic Yards Community aware of upcoming construction activities, ESD and Forest City Ratner provide the following outline of anticipated upcoming construction activities.
Please note: the scope and nature of activities are subject to change based upon field conditions. All work has been approved by appropriate City and State agencies where required.
In addition to the activities described below noise attenuation and vibration monitoring measures are underway in connection with the Memorandum of Environmental Commitments dated 12/08/06.
If you have any questions please feel free to contact our project Ombudsperson at: 212-803-3233 or AtlanticYards@empire.state.ny.us.
Long Island Rail Road/Vanderbilt Yard Work
Continue construction and debris removal from Block 1121.
Continue hauling soil from Blocks 1120 and 1121.
Continue sloping soil, Block 1121.
Continue installing gabion wall, Block 1121.
Complete east abutment.
Continue assembly of temporary train trestle/bridge on Block 1121.
Abatement and Demolition Work
All work described below will comply with the additional oversight and protocols by the Department of Buildings (DOB) that were established on April 30, 2007.
- Demolition is underway at 800 Pacific Street (block 1129, lot 25) and will continue throughout this two week period.
Utility Work
All utility work scheduled to take place in Flatbush Avenue will only take place at night (between 10PM and 6AM) as mandated by DOT.
- Transit ducts on Flatbush Avenue between Atlantic Avenue and Dean Street have been relocated. Cable will be pulled in the new transit ducts. This work is expected to continue over the next month. All work taking place in the sidewalk will occur during the day. Pedestrian walkways will be maintained.
Private Utility Work
The work described below is managed and contracted by the respective private utility companies, as indicated.
- Verizon will be splicing cable on Pacific Street between Flatbush and 6th Avenues and removing cable at Atlantic and Flatbush Avenues.
Posted by eric at November 18, 2008 8:46 PM