News analysis: The Times gives the ESDC a bye

Atlantic Yards Report

Norman Oder oderizes The Times's coverage of the Hudson Yards deal:

A New York Times News Analysis today of the West Side Yards deal, headlined :For Railyards, the Hard Part Is Still Ahead, leaves out some important Atlantic Yards context:

In the end, the project could take well over a decade to complete, and its look could change significantly from the current designs by Helmut Jahn and Peter Walker.

In Brooklyn, the developer Bruce Ratner has already acknowledged that his $4 billion Atlantic Yards project will take longer than the 10 years originally envisioned.

First, the Times should have pointed out that, not only has Ratner acknowledged that the project would take longer than ten years, others in his firm and outside observers had been making the same observation, and that the Empire State Development Corporation (ESDC) has given some generous deadlines: 6+ years to build the arena, 12+ years to build the first five towers, and an unspecified amount of time to build the rest.

Also, whatever Yaro says applies equally well to Atlantic Yards. If built, it will change significantly from Frank Gehry's renderings.