« Ward Bakery | Main | The Ratnerville Demolition Hot Spot Map, September 10-17 »

September 11, 2007

ATLANTIC YARDS RATNERVILLE CONSTRUCTION UPDATE

The Atlantic Yards demolition block and lot map here.

ATLANTIC YARDS CONSTRUCTION UPDATE
Weeks WEEK of September 10, 2007 – September 17, 2007

In an effort to keep the Atlantic Yards Ratnerville Community aware of upcoming construction activities, ESD and Forest City Ratner are providing the following outline of anticipated upcoming construction activities.

Please note: the scope and nature of activities are subject to change based upon field conditions.

Long Island Rail Road/Vanderbilt Yard Work

AY-Block1121lot1.jpg

  • Mid-block piles: Drilling is complete; excavating down a few feet then installing lagging
  • Excavation of material and preparation to drill piles at Southeast Gas Station (block 1121, lot 47)
  • Continue test piles for Temporary Train Trestle foundation piles.

  • Continue test pits on Pacific Street within the area which has already been closed (see photo) pursuant to the Pacific Street Maintenance and Protection of Traffic Plan (MPT) on block 1121 to confirm location of existing street utilities proximate to layout of piles.
  • Mobilization to East Portal; preparation for drilling of piles.
  • Mobilization to drill foundation piles for cable bridge (adjacent to 6th Avenue Bridge).
  • Continue soil excavation and removal in block 1121 west to east.
  • Continue construction and debris removal.

Abatement and Demolition Work

All work described below will comply with the additional oversight and protocols by the Department of Buildings (DOB) that were established on April 30th.

Posted by lumi at September 11, 2007 9:32 AM