If we didn't know better, we'd swear that Atlantic Yards encyclopedia Norman Oder sounds a little testy because the Empire State Development Corporation scuttled his plans for a quiet weekend catching up on a little light reading.
So much for a quiet Thanksgiving weekend. Consultants working on the Atlantic Yards Final Environmental Impact Statement (FEIS), which had to be revised to incorporate comments that were missed in the first version released November 15, will have it ready for a 9 a.m. meeting Monday of the board of the Empire State Development Corporation (ESDC), the agency confirmed.
The board again will be asked "to determine that the FEIS is complete," and again will say so. Clearly, that's just a formality. We can't expect the board to actually compare the lengthy document at hand with, for example, the comments submitted.
Posted by lumi at November 23, 2006 8:20 AM